From foundation to cabin set. Construction is complete. Track what was done, the one item still open, and the evidence behind each date.
John Pickett, Project Manager · john@halohalollc.com · 503-379-1474.
Logistics backup: Chad Crosby · halohalologistics@gmail.com · 503-201-1048. Office: 503-914-6566.
Loaded Oct 26, arrived on site the evening of Oct 28, offloaded and crane-set Oct 29. Signed bill of lading received Oct 30; transport $9,421 paid.
Curated photos and short field clips are tied to the same workstreams as the construction schedule. Select a chapter or a media badge in the Gantt.
Tap a vendor for contract detail and timeline.
Grouped by month. Latest month open.
One line per topic. Tap for the detailed items.
Grouped by type, with counts. Tap to list each source.
October 7 is the owner-report date, not the exact pour, pad or siding completion date; foundation-wall images are dated October 1. The cabin arrived the evening of October 28 and was crane-set October 29; installation complete and the signed bill of lading are both dated October 30. Utility connection and mechanical, electrical and plumbing completion are owner-reported November 12; the exact hookup date was not supplied, so that Gantt bar ends at the report date.
The Town Certificate of Occupancy is scheduled for the week of November 30 and is the only open item; the December 5 go-live marker follows from it and is indicative, not a booked date. The County Sewage Treatment System Certificate of Approval (Oct 13) and National Grid close-out (Sep 23) are separate, completed approvals. Owner confirms November 23 that all payments are made and the project carries no debt: all-in $273,008.37, itemized on /juniper-complete.