VGH · Unplugged Cabins · Construction board

Juniper Ridge
Construction Timeline

From foundation to cabin set. Construction is complete. Track what was done, the one item still open, and the evidence behind each date.

Site 764 Blenheim Hill Rd, Jefferson NY
Parcel 432000 170.-1-2.28
As of 2026-11-23
Cabin delivered 2026-10-29
Go-live After CO

Gantt · contract to live

Nov 23 update · construction complete, paid in full. The cabin was delivered and crane-set on its foundation Oct 29; owner confirmed installation complete Oct 30. All mechanical, electrical and plumbing work is done, and the house is connected to its well and National Grid power with every system running. All payments are made and the project carries no debt: all-in $273,008, including the $118,500 modular unit, $62,150 sitework, $9,592 well, $9,421 transport and $6,500 National Grid / electrical. The County sewage-treatment Certificate of Approval is dated Oct 13. The only open item is the Town Certificate of Occupancy, scheduled for the week of Nov 30; go-live follows it. Cost summary → · Evidence & caveats ↓
Delivery desk · delivered Oct 29

Halo Halo Logistics contacts

John Pickett, Project Manager · john@halohalollc.com · 503-379-1474.

Logistics backup: Chad Crosby · halohalologistics@gmail.com · 503-201-1048. Office: 503-914-6566.

Loaded Oct 26, arrived on site the evening of Oct 28, offloaded and crane-set Oct 29. Signed bill of lading received Oct 30; transport $9,421 paid.

Field journal

Build story

Curated photos and short field clips are tied to the same workstreams as the construction schedule. Select a chapter or a media badge in the Gantt.

Vendors & contracts

Tap a vendor for contract detail and timeline.

Milestone log

Grouped by month. Latest month open.

Assumptions

One line per topic. Tap for the detailed items.

Sources

Grouped by type, with counts. Tap to list each source.

Footnotes

Dates & evidence

October 7 is the owner-report date, not the exact pour, pad or siding completion date; foundation-wall images are dated October 1. The cabin arrived the evening of October 28 and was crane-set October 29; installation complete and the signed bill of lading are both dated October 30. Utility connection and mechanical, electrical and plumbing completion are owner-reported November 12; the exact hookup date was not supplied, so that Gantt bar ends at the report date.

Open item · payments

The Town Certificate of Occupancy is scheduled for the week of November 30 and is the only open item; the December 5 go-live marker follows from it and is indicative, not a booked date. The County Sewage Treatment System Certificate of Approval (Oct 13) and National Grid close-out (Sep 23) are separate, completed approvals. Owner confirms November 23 that all payments are made and the project carries no debt: all-in $273,008.37, itemized on /juniper-complete.